Latest Site News & Updates
278 Works
16/06/2011
278 works to the Peasley cross road site entrance work ongoing and will be complete on programme.…
Read More…
Retail Carpark
16/06/2011
Retail carpark progressing well, all the drainage and kerbing work is in place and the road surface …
Read More…
Roofing
16/06/2011
Roofing works to the stadium south stand are well progressed, work on the west stand ongoing. Week c…
Read More…
Drainage
16/06/2011
All deep drainage works have been completed, Tesco store drainage 100% Stadium drainage internally 1…
Read More…
Brickwork/Blockwork
16/06/2011
Blockwork has started to the stadium, externally on the diaphraghm wall. Internally blockwork progre…
Read More…
Cladding and curtain walling
16/06/2011
Cladding and curtain walling has started on the south elevation this is progressing well and will be…
Read More…
Landscaping and Fencing
16/06/2011
Landscaping has started to the Tesco car park area and public realm works adjacent to the SAM, this …
Read More…
Steelwork
07/04/2011
Stadium Started on the South stand and is progressing well, will be complete on programme. Concre…
Read More…
Drainage
07/04/2011
Drainage works are ongoing on sections 1,2 and 3 thiese woprks are progressing as per the programme.…
Read More…
Archaeology
07/04/2011
The final report is now being compiled, and has been submitted and accepted by all of the relevant p…
Read More…
Electrical
07/04/2011
Sub-station is now complete. Scottish power have started the internal fit out for the transformer ro…
Read More…
Roofing - Store
07/04/2011
The roofing works and cladding have now started on the Tesco retail unit this will progress over the…
Read More…
Retail Car Park works
07/04/2011
The kerbing, duct work have started in this area and will continue for the next six weeks, drainage …
Read More…
278 Works
07/04/2011
278 works on the adjoing roads to the South, East and West have been completed. The entrance road fr…
Read More…
Interesting Project Facts...
05/04/2011
The New St Helens Stadium will contain...
- Earth moved – Cut 26,075m3, Fi…
Read More…
Electrical Infrastructure
21/02/2011
Foundations now complete. Brickwork to super structure has started and is progressing well. Precast …
Read More…
Piling
21/02/2011
The vibro piling for the store has been completed for the first visit, the second visit is due frida…
Read More…
Cut & Fill
21/02/2011
Cut & fill to the West car park progressing well. Any remaining cut and fill be carried to accomo…
Read More…
Mains Gas Diversion
21/02/2011
The new Governor arrived last week and has now been fitted. The new governor has been commissioned a…
Read More…
Archaeology
21/02/2011
The further investigations have been completed, there has been a report compiled with recomendations…
Read More…
Foundations
21/02/2011
Excavation for foundations and concreting for the Tesco store have progressed well and are on progra…
Read More…
Drainage
21/02/2011
Drainage works have commenced with connection to the surface and foul water at section 3, this work …
Read More…
steelwork
21/02/2011
The Tesco store steelwork will arrive on site week commencing the 7th March 11 and will start from t…
Read More…
Demolition
21/01/2011
Demolition work is completed in phase 1 all the buildings have been taken down. The four concrete sl…
Read More…
Archaeology
21/01/2011
The archaeologists have carried out further investigations to the East of the SAM to ascertain the c…
Read More…
Mains Gas Diversion
21/01/2011
Mains Gas Diversion has progressed well they have now connected the new gas pipe bypass into the exi…
Read More…
Cut & Fill
21/01/2011
The cut and fill for both the Stadium and the Store has progressed well and has been completed to fo…
Read More…
Electrical Infrastructure
21/01/2011
Scottish Power have progressed the laying of their electrics HV main from the South West corner of t…
Read More…
Grouting works
21/01/2011
All grouting works to mine workings have been completed, the mine shafts have been capped.…
Read More…
Piling
21/01/2011
Vibro piling works have started on programme, small section of Vibro in the Stadium on the North par…
Read More…
Cut & Fill
23/12/2010
Stadium footprint has been cut to formation level, as have surrounding car parks and walkways.…
Read More…
Archaeology
23/12/2010
Additional archaeological investigation currently taking place, to discover the extent of undergroun…
Read More…
Demolition
22/11/2010
Demolition works complete including floor slabs. Demolition networks have now moved on to phase 2 ta…
Read More…
Site Security
22/11/2010
Site security is now fully functional with perimeter cameras in place around the whole site.…
Read More…
Gas main diversion
22/11/2010
Making good progrerss and now moved onto the southwest part of the site.…
Read More…
Grouting Works
22/11/2010
Has made good progress, they will be moving out of main site area down to basement area to grout sec…
Read More…
Electrical infrastructure
22/11/2010
moving along nicely, looking to enter into the site on the southwest corner over the next week.…
Read More…
Recycling of site one material
22/11/2010
concrete floor slab will be crushed this week to make type 1, this will cover the stadium and the st…
Read More…
Gas Main Diversion
18/11/2010
High pressure and medium pressure gas main diversion to allow Tesco store to be built. This work was…
Read More…
Electrical Infra Structure
18/11/2010
Electrical infra structural works are currently being undertaken from Tall Tress along the linkway &…
Read More…
Archaeology
18/11/2010
Works commenced around the scheduled Ancient Monument (SAM) and 14 exploratory trenches were dug to …
Read More…
Grouting Works
18/11/2010
Grouting works have started to the underlying mine works (1st November 2010) this has been successfu…
Read More…
Cut & Fill
18/11/2010
Cut & fill excercise in ground stabilisation starting on schedule Monday 15th November 2010…